 March 14, update

*  Concrete work is complete and the crew now moves to straightening the building and stiffening the walls and roof. 

*  Narthex - seismic upgrade to stiffen front end of building and strengthen organ loft.  See photo

*  Scaffolding in place to provide access to the large rods that will pull the building back into shape. Expected to be done this week.   See photo

*  The new slab has been poured for the transept extension. All other foundation work is now complete.    See photo

*  Drains in place to collect rainwater from roof and drain tile around foundations.  See photo.